Enter 16 points.
Voltage and current: 6/14mA DC12/24V.
Response time: 0.2ms.
16 point /1 public end, 20 point terminal.
Detailed analysis of the process and work characteristics of the controlled object,
To understand the coordination between the controlled object machine, electricity and liquid,
The control requirements of the controlled object for MITSSUBISHI PLC control system are put forward,
Determine the control program, to develop a design task book A1S68B-S1.
How to determine the input / output device of MITSUBISHI plc A1S68B-S1.
According to the control requirements of the system,
All input devices and output devices required for the determination of the system,
To determine the input / output device related to the MITSUBISHI PLC,
To determine the I/O PLC points A1S68B-S1. MITSUBISHI PLC hardware implementation
Hardware implementation is mainly for the control cabinet and other hardware design and field construction.
Design control cabinet and the operating table and other parts of the electrical wiring diagram and wiring diagram.
Electrical interconnection diagram of each part of the design system MITSUBISHI A1S68B-S1.
According to the construction drawings of the site wiring, and carry out a detailed inspection.
Because the program design and hardware implementation can be carried out at the same time,
So the design cycle of the MITSUBISHI PLC control system can be greatly reduced MITSUBISHI A1S68B-S1.
I/O slots: 8 slots.
Could you install the power module.
Outline dimension: 420*130.
There are two types of extended floor,
A power module can be inserted, and the other one is not.
The choice of any type of substrate depends on the total DC5V current consumption and the power supply on the CPU main substrate MITSUBISHI A1S68B-S1.
If the total demand is less than the power output, no additional power supply,
Then you can choose a more economical expansion board.
Both ends of the main base plate of the CPU have an expansion interface, and can be used for extending the cable connection. DC input points: 4 points.
Input voltage and current: 7mA, DC24V.
Input response time: 10ms.
4 point /1 a public side.
Positive / negative sharing.
Output points: 4 points.
Output voltage and current: DC24V/AC240V, 2A/1 point, 8A/1 common end.
Output response time: 12ms.
4 point /1 a public side.
Output form: relay.
24 point terminal station.
MITSUBISHI PLC protection and chain procedures.
Protection and chain is an indispensable part of the program, must be carefully considered.
It can avoid the control logic confusion caused by illegal operations.
MITSUBISHI PLC initialization procedure. After MITSUBISHI PLC on power, the general need to do some of the initial operation,
In order to start making necessary preparations, to avoid the wrong operation of the system.
The main contents of the initialization program are: to some data area, counter and so on,
Data needed to restore some of the data area,
Set or reset some relays,
For some initial state display, etc..
MITSUBISHI PLC program simulation debugging
The basic idea of program simulation debugging is,
In order to facilitate the form of simulation to generate the actual statee of the scene,
Create the necessary environmental conditions for the operation of the program A1S68B-S1.
Depending on the way the field signals are generated,
The simulation debugging has two forms of hardware simulation and software simulation.